Facilities Projects

The Facilities Services team manages a variety of projects across the College. 

Explore our active projects and learn about what's being planned for campus in the future. In this section you can find project updates and information about our major projects and current construction contracts. You can also find details about our Comprehensive Campus Plan. 

February 2025 Updates

Project Updates as of March 21, 2025

Description: Seminar Room 111 will be converted into an accessible graduate student lounge.

Status: This project awarded and demolition began over spring break.  There will be limited construction activity until the end of the semester

Impacts: There will be some construction activity and intermittent noise. Room 111 is off-line.

Description: We continue the phased renovation of Park Science that now includes renovations to the Collier Library and select areas of the Biology  wing.

Status: The areas now under construction, including the Biology wing and the Collier Library, are now isolated.  Construction will be completed by the fall semester 2025.

 Impact: There will be some intermittent noise. We are working with those affected to manage the impacts.  Any utility interruptions as noted above will be planned and communicated in advance with the affected groups. The Biology east stair well be closed for spring semester.

Description: The motor in one Chemistry wing air handling unit in Park Science will be replaced.

Status: The  initial work was  initiated over break.  We are awaiting parts to complete the projects.

 Impacts: The air handling unit  is operating in a modified state and the completion of the project is being coordinated with the effected users.

 

Description: Rebuild Rhoads Patio, rebuild the waling path and regrade to make the patio accessible.  Landscaping will also be installed.

Status: TWork has  resumed on  the project over spring break..

Impacts: There will be some noise. The most noisy operations will be limited to after 8:00 am

Description: Plants will be installed in the Cloisters.

Status:The plants will be delivered the week of  March 31, final layout and planting will be done the week of April 7.

 Impacts:  Minimal. 

 

Description:  Replace temporary thresholds with permanent thresholds in guest rooms

Status:  Scheduled for March 31, 20205.

 Impacts:  This will impact room availability and is coordinated with Wyndham staff.

 